Six of eight buildings at the 1.2 GW Stargate campus in Abilene were delivered by September 2026. See who is building the three Texas sites and what they cost.

Quick Answer: The Stargate flagship in Abilene is an eight-building, 1.2 gigawatt campus built by Crusoe, with Oracle supplying the computing hardware and OpenAI as the user. Oracle said on September 10, 2026 that six of the eight buildings had been delivered, and Crusoe’s stated target for the full campus is the end of 2026. Two more Texas Stargate campuses, in Shackelford County and Milam County, are under construction with completion projected for 2028.

Texas holds three of the seven United States sites that have been publicly tied to Stargate, the artificial intelligence infrastructure program that OpenAI, SoftBank, Oracle and the investment firm MGX announced at the White House on January 21, 2025. The first and most advanced is in Abilene, in Taylor County. The second sits just across the county line in Shackelford County. The third is in Milam County, about 70 miles northeast of Austin.

This article sets out what the companies have disclosed and what independent trackers have observed as of November 17, 2026. Where the newest confirmed information is older, the date is stated.

What is Stargate, and who is behind the Texas sites?

OpenAI’s January 2025 announcement described Stargate as a plan to invest $500 billion over four years in United States AI infrastructure, with $100 billion to be deployed immediately. It named SoftBank, OpenAI, Oracle and MGX as the initial equity funders. SoftBank took financial responsibility and OpenAI took operational responsibility, with SoftBank’s Masayoshi Son as chairman. The announcement said the buildout was already underway, starting in Texas.

Each Texas campus has a different set of builders and owners. The usual structure has three layers: a developer that owns the buildings and power infrastructure, a company that owns the chips, and OpenAI as the user.

Site Developer Hardware owner Announced capacity Status
Abilene (Taylor County) Crusoe, on the Lancium Clean Campus Oracle 1.2 GW, 8 buildings 6 of 8 buildings delivered as of September 10, 2026
Shackelford County (“Frontier”) Vantage Data Centers Oracle (per Epoch AI) 1.4 GW, 10 buildings Under construction; first building scheduled for second half of 2026
Milam County SB Energy, a SoftBank Group company SoftBank (per Epoch AI) 1.2 GW Under construction; projected completion in 2028

How big is the Abilene campus?

Crusoe, the developer, describes the Abilene site as eight buildings with about 4 million square feet of space and 1.2 gigawatts of total power capacity. It was built in two phases on the Lancium Clean Campus.

What was built in each phase?

Phase one consists of two buildings totaling 980,000 square feet with more than 200 megawatts of capacity. Crusoe says construction began in June 2024. Phase two, announced on March 18, 2025, added six buildings and took the planned campus to 1.2 gigawatts.

Crusoe topped out the eighth and final building in November 2025, according to trade publication W.Media.

How was it paid for?

On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced a $15 billion joint venture to fund the campus through its second phase. That figure covers the buildings and supporting infrastructure, not the chips inside them.

The chips are the larger expense. Epoch AI, a research organization that tracks large AI data centers using satellite imagery, permits and company statements, estimates the capital cost of the completed Abilene campus at $31.2 billion. That is an outside estimate.

What chips are running in Abilene?

The Abilene campus runs on Oracle Cloud Infrastructure. OpenAI and Crusoe both said Oracle began delivering Nvidia GB200 racks to the site in June 2025, and that early training and inference workloads had started by that summer.

Crusoe’s releases state that each of the eight buildings is designed to operate up to 50,000 Nvidia GB200 NVL72 systems on a single integrated network fabric. Across eight buildings, that design figure implies up to 400,000 units.

How is computing capacity measured?

Because chip generations differ in performance, Epoch AI converts everything to a common unit it calls the H100-equivalent, the computing output of one Nvidia H100 processor. On that measure, Epoch’s tracker, last updated November 1, 2026, puts the full Abilene campus at about 1.02 million H100-equivalents and 824 megawatts of IT power. Epoch lists the chips as Nvidia B200 and B300 models, which is its own estimate.

The gap between 824 megawatts and 1.2 gigawatts is a matter of definitions. IT power counts only the electricity delivered to computing equipment. Total facility power also includes cooling and other building loads.

Is the Abilene campus finished?

Completion had not been confirmed as of November 17, 2026. The most recent company statement on record is from Oracle’s quarterly earnings call on September 10, 2026. According to Epoch AI’s summary of that call and a published recap of it, Oracle said six of the eight Abilene buildings had been delivered to the customer, representing 618 megawatts or 75% of the campus’s capacity.

Oracle did not give a date for the final two buildings. Epoch’s tracker estimates that buildings seven and eight became operational around the start of November 2026, but it labels that entry a projection and not a confirmed fact.

Date Abilene milestone Source
June 2024 Construction begins on phase one (two buildings) Crusoe
March 2025 Phase two announced and started: six more buildings, 1.2 GW total Crusoe
June 2025 Oracle begins delivering Nvidia GB200 racks OpenAI, Crusoe
November 2025 Eighth and final building topped out W.Media
March 2026 OpenAI declines further Abilene expansion; Microsoft takes adjacent 900 MW site Associated Press, Crusoe
September 10, 2026 Oracle reports six of eight buildings delivered (618 MW) Epoch AI, BigGo Finance recap
Early November 2026 Buildings seven and eight estimated operational (unconfirmed) Epoch AI

The schedule has slipped modestly. Crusoe’s 2025 releases targeted mid-2026 for the second phase. Its March 27, 2026 release said the end of 2026.

Why did OpenAI stop expanding in Abilene?

When OpenAI, Oracle and SoftBank announced five additional Stargate sites on September 23, 2025, the list included a potential 600 megawatt expansion near the Abilene flagship. That expansion did not go ahead for OpenAI. Bloomberg first reported on March 6, 2026 that the plan had been dropped, according to Tom’s Hardware, and Oracle responded that the existing site remained on schedule.

The Associated Press reported on March 27, 2026 that OpenAI chose to put additional capacity in other locations. The same day, Crusoe announced that Microsoft would take the adjacent site.

What is Microsoft building next door?

Crusoe’s release describes a 900 megawatt campus for Microsoft with two new buildings, each designed for 336 megawatts of critical IT load, plus a 900 megawatt on-site power plant paired with battery storage. The first building is expected to be energized in mid-2027.

With it, the combined Abilene development reaches 10 buildings and about 2.1 gigawatts, according to Crusoe and the Associated Press. The AP also reported that the Stargate campus has a 350 megawatt gas-fired plant on site, which Oracle describes as backup.

How many jobs has the Abilene project created?

The verified figures are construction headcounts, and they rose as the project scaled. Crusoe said about 2,000 people were working on site daily in March 2025 and about 3,000 in May 2025, with nearly 5,000 expected during phase two. By November 2025, Crusoe was crediting 7,000 electricians, construction professionals and skilled tradespeople, according to W.Media.

Crusoe has not published a permanent operations headcount in the releases reviewed here. Its March 2026 release projected that the eight buildings would deliver up to 32% of the City of Abilene’s and up to 25% of Taylor County’s fiscal 2025 budgeted property tax revenue.

What is being built in Shackelford County?

Vantage Data Centers announced the Frontier campus on August 19, 2025, calling it an investment of more than $25 billion and the largest in the company’s history. The plan covers 1,200 acres with 10 data center buildings totaling 3.7 million square feet and 1.4 gigawatts of capacity.

OpenAI named Shackelford County as an Oracle-developed Stargate site on September 23, 2025.

How does Frontier differ from Abilene?

Frontier is designed for denser hardware. Vantage says the buildings will support racks drawing more than 250 kilowatts each, using liquid cooling and a closed-loop chiller system that needs minimal water. Epoch AI reports that the campus will be powered by an on-site natural gas microgrid.

Epoch also offers a different capacity number. Vantage’s 1.4 gigawatts refers to IT power. Epoch estimates total facility power at about 2 gigawatts, and projects roughly 4.2 million H100-equivalents of computing when the site is complete. That projection rests on assumptions about future chip efficiency.

When will Frontier open?

Vantage’s schedule calls for the first building to be delivered in the second half of 2026, and Epoch AI projects full completion in late 2028. Vantage projects more than 5,000 jobs across construction and ongoing operations. Oracle’s September 10, 2026 call indicated Shackelford had not yet contributed to its delivered capacity, according to a published recap. No confirmation that the first building has been handed over was found as of November 17, 2026.

What is planned for Milam County?

The Milam County campus follows a different model, with SoftBank in place of Oracle. OpenAI’s September 2025 announcement said the site would be developed with SB Energy, a SoftBank Group company that provides the powered infrastructure.

On January 9, 2026, OpenAI and SoftBank Group said they would each invest $500 million in SB Energy, $1 billion in total. OpenAI signed a 1.2 gigawatt data center lease for the initial Milam County buildout, and SB Energy will build and operate the site. The $1 billion is an investment in SB Energy as a company, not the construction budget for the campus, and no total project cost has been disclosed.

OpenAI said the site will create thousands of construction jobs and that new generation is planned to meet its energy needs. Epoch AI’s April 2026 review found steel framing and roofing on the first building in a March satellite image, cited regulatory filings indicating first-building delivery by October, and projected full completion in the fourth quarter of 2028. No later confirmed milestones were found.

How do the three Texas sites add up?

At the companies’ announced figures, the three Texas campuses total 3.8 gigawatts: 1.2 in Abilene, 1.4 in Shackelford County and 1.2 in Milam County. Epoch AI’s April 2026 review counted more than 9 gigawatts of projected capacity across seven United States Stargate sites, using its own total-facility estimates.

The disclosed funding figures are not comparable. Abilene’s $15 billion is a real estate joint venture, the more than $25 billion in Shackelford County is a developer’s campus commitment, and the $1 billion tied to Milam County is a corporate equity investment.

Brian’s Take

What stands out to me in these numbers is speed. Crusoe started moving dirt in Abilene in June 2024, and by September 2026 Oracle was telling investors that six of eight buildings were in the customer’s hands. A slip from mid-2026 to the end of 2026 on a 1.2 gigawatt campus looks modest to me for a project this size.

I would also pay attention to who owns what. In Abilene, one company owns the buildings, another owns the chips and a third uses them. In Milam County, SoftBank’s side holds both the site and the hardware. OpenAI passing on the Abilene expansion in March 2026 shows that plans at this scale do get revised.

For Texas business owners, I think the practical point is that the construction payroll is the verified part of the jobs story so far: 7,000 workers at the Abilene peak reported in late 2025. Permanent staffing numbers for these campuses have mostly not been published.

Frequently Asked Questions

Who owns the Stargate data center in Abilene?

Crusoe developed the campus, funded through a $15 billion joint venture with Blue Owl Capital and Primary Digital Infrastructure. Oracle owns the chips and runs the site on Oracle Cloud Infrastructure. OpenAI is the user.

Is Microsoft part of Stargate in Abilene?

No. Microsoft is the customer for a separate 900 megawatt, two-building Crusoe campus next to the Stargate site, announced on March 27, 2026 after OpenAI chose not to expand there. Its first building is expected to be energized in mid-2027.

Where are the other Texas Stargate sites?

Vantage Data Centers is building the 1.4 gigawatt, 10-building Frontier campus in Shackelford County. SB Energy, a SoftBank Group company, is building a 1.2 gigawatt campus in Milam County. Both are projected to be completed in 2028.

How much is being invested in Texas Stargate sites?

There is no single official Texas total. Disclosed figures include the $15 billion Abilene joint venture, Vantage’s commitment of more than $25 billion for Frontier, and $1 billion invested in SB Energy by OpenAI and SoftBank. Epoch AI separately estimates Abilene’s full capital cost at $31.2 billion.

Sources and Further Reading

  1. Announcing The Stargate Project, OpenAI
  2. Stargate advances with 4.5 GW partnership with Oracle, OpenAI
  3. OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites, OpenAI
  4. OpenAI and SoftBank Group partner with SB Energy, OpenAI
  5. SB Energy to Build Stargate Data Center in Texas, SB Energy
  6. Crusoe Expands AI Data Center Campus in Abilene to 1.2 Gigawatts, Crusoe
  7. Crusoe, Blue Owl Capital and Primary Digital Infrastructure Enter Joint Venture, Crusoe
  8. Crusoe Announces Flagship Abilene Data Center is Live, Crusoe
  9. Crusoe Announces New 900 MW AI Factory Campus in Abilene, Texas to Support Microsoft AI Infrastructure, Crusoe
  10. Vantage Data Centers Unveils Plans for “Frontier,” a $25B Mega-campus in Texas, Vantage Data Centers via Business Wire
  11. OpenAI Stargate: where the US sites stand, Epoch AI
  12. OpenAI Stargate Abilene data center tracker entries, Epoch AI
  13. Microsoft takes over a Texas AI data center expansion after OpenAI backs away, Associated Press
  14. Oracle and OpenAI scrap planned 600MW Abilene expansion, Tom’s Hardware
  15. Crusoe tops off final AI data center in Abilene, Texas, W.Media
  16. Oracle Q1 2027 Earnings Call summary, BigGo Finance