Texas has spent five years trying to turn a wave of chip-factory announcements into working production lines. AI servers need leading-edge logic chips, but they also need power and analog chips, optical parts, test hardware and raw silicon wafers. This report reviews where the largest Texas semiconductor projects stand as of November 18, 2026, using company releases, state grant records and federal CHIPS program documents.
Which Texas chip fabs are actually producing today?
Two of the three headline projects are operating. Texas Instruments began production at SM1, the first fab at its Sherman site, and marked the opening on December 17, 2025. GlobalWafers opened its 300-millimeter silicon wafer plant in Sherman on May 15, 2025. Samsung’s Taylor fab, the only one of the three aimed at leading-edge AI processors, has not yet entered production.
| Project | Announced investment | What it makes | Status (Nov. 2026) |
|---|---|---|---|
| Samsung, Taylor | More than $37 billion in the region (federal CHIPS record) | 2-nanometer logic foundry chips | First fab not yet producing; mass production planned for 2027; second fab targeted for 2030 |
| Texas Instruments, Sherman | Up to $40 billion for four fabs | Analog and embedded processing chips on 300mm wafers | SM1 in production since December 2025; SM2 construction complete |
| Texas Instruments, Richardson | $700 million expansion (state grant record) | Analog chips on 300mm wafers | Expansion announced July 9, 2026 |
| GlobalWafers, Sherman | $3.5 billion initial; $7.5 billion planned U.S. total | 300mm silicon wafers | Open since May 2025; next phase in design |
Where does Samsung’s Taylor fab stand?
Samsung selected Taylor in November 2021 for its first dedicated U.S. foundry site, with an initial investment of about $17 billion. Construction began in 2022 and the company originally targeted operations in the second half of 2024. The schedule has slipped by roughly two years, according to a November 8, 2026 report in The Korea Herald.
Samsung confirmed in late October 2026 that the first Taylor plant is expected to be fully operational by year-end. The same report, citing industry sources, said trial runs could begin as early as December 2026, a date Samsung has not confirmed. Mass production is planned for 2027.
What will Samsung make in Taylor, and for whom?
The Taylor plan changed from its original design. When Governor Greg Abbott announced a $250 million Texas Semiconductor Innovation Fund grant to Samsung Austin Semiconductor on September 17, 2025, the state said the facility would shift to manufacturing 2-nanometer leading-edge logic chips, backed by a $4.73 billion capital investment in that initiative. The state named 5G, AI and high-performance computing as target uses.
The anchor customer is Tesla. Under a $16.5 billion supply agreement announced in 2025, Samsung is to produce Tesla’s next-generation AI6 chip at Taylor, with that production planned for the second half of 2027, The Korea Herald reported. A July 13, 2026 report from South Korea’s Financial News said Samsung planned to send a second team to Taylor by September 2026 for yield verification and mass-production support. The Korea Herald report noted that yields, the share of working chips per wafer, need to stabilize before volume production.
Is Samsung building a second Taylor fab?
Yes. Samsung said on its second-quarter 2026 earnings call that it would begin construction on a second Taylor fab by the end of 2026, with mass production targeted for 2030, according to an August 5, 2026 GlobalSpec report.
The federal record matches that two-fab plan. The CHIPS Program Office’s page for Samsung, last updated September 10, 2026, lists a final award of up to $4.745 billion in direct funding to Samsung Austin Semiconductor, supporting more than $37 billion of expected investment in the region. The award covers two leading-edge logic fabs for 2-nanometer production and a research and development fab in Taylor, plus an expansion of Samsung’s existing Austin plant for fully depleted silicon-on-insulator technology serving aerospace, defense and automotive customers. The page lists more than 3,500 manufacturing jobs and 12,000 construction jobs and says all facilities are expected to be operational by 2030.
What is Texas Instruments building in Sherman and Richardson?
Texas Instruments’ plan is larger in dollars than Samsung’s but aimed at a different part of the market. On June 18, 2025, the company said it plans to invest more than $60 billion across seven U.S. fabs in Texas and Utah, including up to $40 billion for four connected fabs in Sherman, labeled SM1 through SM4. It named Apple, Ford, Medtronic, NVIDIA and SpaceX as customers.
These are foundational chips, not AI processors. Federal award documents describe the Sherman fabs as producing chips on 65-nanometer to 130-nanometer process technology. The products are analog and embedded processing chips, and the company said analog power products were among the first made at Sherman.
How far along is the Sherman site?
- SM1: In production. The company broke ground on May 18, 2022, and said on December 17, 2025 that customers were receiving chips from the fab, three and a half years after groundbreaking. Output will ramp with customer demand, and the company says SM1 will ultimately produce tens of millions of chips daily.
- SM2: Construction is complete, according to the company’s manufacturing page.
- SM3 and SM4: Planned as incremental investments to support future demand.
- Site totals: The company’s Sherman page lists 1.3 million square feet of cleanroom space and about 3,000 company jobs.
In Richardson, where the company’s RFAB1 opened in 2009 and the connected RFAB2 started production in 2022, the state added a new grant this year. Governor Abbott announced a $33.6 million Texas Semiconductor Innovation Fund grant on July 9, 2026 for expanded capacity and technology investments at the Richardson 300mm fab, a project the state said is expected to total $700 million in capital investment.
On the federal side, Texas Instruments’ final CHIPS award was $1.61 billion, supporting about $18 billion of investment through 2029 at three fabs: SM1 and SM2 in Sherman and LFAB2 in Lehi, Utah. That award is therefore not all Texas money.
What is GlobalWafers doing in Sherman?
GlobalWafers supplies the raw material. The Taiwan-based company opened its Sherman plant on May 15, 2025 after deciding on a U.S. facility in May 2022 and breaking ground in December 2022. The plant makes 300-millimeter silicon wafers, the blank discs that fabs turn into chips. The initial investment was $3.5 billion, and at the opening the company announced a further $4 billion for its U.S. operations, bringing the planned total to $7.5 billion. The Sherman campus covers 142 acres and is designed to hold up to six phases.
When the Commerce Department announced preliminary terms with GlobalWafers in July 2024, it said five companies hold more than 80% of the global 300mm wafer market and that about 90% of silicon wafers were sourced from East Asia. The company’s CHIPS award is $406 million, which also supports a plant in St. Peters, Missouri.
On customers, Apple said in August 2025 that it is partnering with GlobalWafers America so that advanced wafers are produced for use in U.S. fabs, and that TSMC’s Phoenix plant and Texas Instruments will use the Sherman plant’s 300mm wafers. The company expects up to 650 employees in Sherman by the end of 2028.
The next step depends on orders. In January 2026, Chairperson Doris Hsu said the company had begun design work on a second phase in Sherman to shorten the schedule once customer commitments are confirmed.
How much has Texas put in through the Texas CHIPS Act?
Governor Abbott signed the Texas CHIPS Act, House Bill 5174, in June 2023. It created the Texas Semiconductor Innovation Fund. The Legislature appropriated $698 million to the fund in June 2023 and added $250 million in June 2025, for about $948 million. Separately, lawmakers appropriated more than $660 million for research and development centers at The University of Texas at Austin and Texas A&M University.
The Governor’s office publishes a running list of announced grants. As of August 25, 2026, it showed:
| Texas Semiconductor Innovation Fund (as of Aug. 25, 2026) | Projects | Grants announced | Capital investment | Jobs |
|---|---|---|---|---|
| Fiscal 2024-2025 | 9 | $68.9 million | $0.93 billion | 662 |
| Fiscal 2026-2027 | 23 | $505.8 million | $9.48 billion | 2,677 |
| Total | 32 | $574.7 million | $10.42 billion | 3,339 |
Samsung’s $250 million grant is the largest on the list and accounts for about 43% of all dollars announced. Subtracting the announced grants from the two appropriations leaves roughly $373 million not yet announced as of that date, a figure calculated for this article and not published by the state. The list also reports $35.3 million in total funds disbursed as of that date, well below the amount announced.
Which grants connect most directly to AI hardware?
Two 2026 awards went to suppliers whose own statements tie them to AI and data center demand:
- Applied Optoelectronics, Sugar Land: $20.85 million, announced April 29, 2026, toward a project of more than $279 million and about 500 jobs making semiconductor chips and optical transceivers for high-speed optical networking. The company linked the investment to AI data center infrastructure.
- FormFactor, Farmers Branch: $24.2 million, announced July 2, 2026, for a new plant making probe cards, which test chips while they are still on the wafer. The company said its customers make logic and memory chips used in AI and data centers. The state list shows 650 jobs.
Brian’s Take
I look at this list the way I used to look at a capital spending pipeline: what is announced, what is built and what is shipping. On that test, Texas has two plants shipping product, both in Sherman, and neither one makes an AI processor. They make power and analog chips and blank wafers. That is not a knock. Those are the unglamorous parts every AI server needs, and they are the parts actually coming out of Texas today.
The leading-edge story is still Samsung in Taylor, and the facts say it is about two years behind its first schedule with one named anchor customer. To me, a fab with a $16.5 billion contract attached is in a much better position than a fab with none, but trial runs are not volume production. I would treat 2027 as the year that matters.
The state money deserves a plain reading too. About 43% of the announced grant dollars went to one company, and only $35.3 million had been disbursed as of late August. The smaller grants to suppliers in Sugar Land and Farmers Branch may tell us more about how deep the Texas supply chain is getting than the headline numbers do.
Frequently Asked Questions
Is Samsung’s Taylor, Texas fab open?
Not for production as of November 18, 2026. Samsung said in late October 2026 that the first plant is expected to be fully operational by year-end, press reports point to trial runs as early as December, and mass production is planned for 2027.
Which Texas fab will make AI chips?
Samsung’s Taylor fab is designed for 2-nanometer logic chips and is slated to produce Tesla’s AI6 chip in the second half of 2027 under a $16.5 billion agreement. Texas Instruments’ Sherman fabs make analog and embedded chips, including power products used in data center equipment.
How much has the Texas Semiconductor Innovation Fund awarded?
The Governor’s office listed $574.7 million in announced grants to 32 projects as of August 25, 2026, tied to $10.42 billion in capital investment and 3,339 jobs.
What does GlobalWafers make in Sherman?
It makes 300-millimeter silicon wafers, the starting material for chips. The plant opened in May 2025 with a $3.5 billion initial investment, and Apple has said TSMC’s Phoenix plant and Texas Instruments will use its wafers.
Sources and Further Reading
- Samsung Electronics (Texas) award page, CHIPS Program Office, National Institute of Standards and Technology
- Announced TSIF Public Listing, as of August 25, 2026, Office of the Texas Governor
- Texas Semiconductor Innovation Fund grant releases for Samsung Austin Semiconductor, Texas Instruments, AOI and FormFactor, Office of the Texas Governor
- Texas CHIPS Office program page, Office of the Texas Governor
- Texas Instruments plans to invest more than $60 billion to manufacture billions of foundational semiconductors in the U.S., Texas Instruments
- Sherman, Texas: 300mm wafer fabs; Worldwide manufacturing; and The future starts with the first, Texas Instruments
- Preliminary Terms with GlobalWafers, National Institute of Standards and Technology
- Apple increases U.S. commitment to $600 billion, announces American Manufacturing Program, Apple
- Samsung’s Texas chip plant could begin trial runs in December, The Korea Herald
- Samsung Electronics completes preparations for mass production of Tesla’s next-generation AI5 chip, Financial News
- Samsung to begin construction on second fab in Texas, GlobalSpec
- Samsung, Texas Instruments and Amkor finalize CHIPS Act funding agreements, Data Center Dynamics
- GlobalWafers to spend additional $4B on US manufacturing, Manufacturing Dive
- GlobalWafers opens Texas wafer plant, announces major expansion, Evertiq
- GlobalWafers Prepares Phase Two Expansion at Texas Wafer Plant, Domain-b